Current Construction Updates
May 11- May 18, 2012
Construction of the new bridge will continue. The new control house is almost complete. Ongoing work includes installation of drainage structures and installation of the steel deck on the movable span of the bridge.
Please Note!
The new bridge remains in the CLOSED POSITION. Please refer to the Mariner Information page for additional information.
Previous Updates
Week of April 1, 2012
Bridge construction will continue this week, including the construction of the control house. Bridge construction, including concrete form work and fender pile installation, will continue this week.
No lane closures are currently planned for this week.
Week of March 25, 2012
Bridge construction, including concrete form work and fender pile installation, will continue this week.
No lane closures are currently planned for this week.
Week of March 18, 2012
Bridge construction, including concrete form work and fender pile installation, will continue this week.
No lane closures are currently planned for this week.
Week of March 11, 2012
Bridge construction, including concrete form work and fender pile installation, will continue this week.